CHILANGA DISTRICT RECEIVES 35 MILLION KWACHA FOR A FULLY FLEDGED SECONDARY SCHOOL

13/08/25

Yesterday, Minister of Defence, Hon. Ambrose Lufuma, officiated at the groundbreaking ceremony for a fully fledged secondary school and teachers’ houses at ZNS Safari Secondary School Grounds, Lusaka West, Kasupe Ward.
Here are the highlights:
✅ The school will be constructed at a cost of K35 million, funded by United Capital Fertilizer Zambia Company Limited, a subsidiary of the Wonderful Group of Companies.
✅ Zambia National Service (ZNS) has partnered in the project by providing land for development.
✅ Hon. Lufuma described the event as symbolising hope, opportunity, and a brighter future for the children of Chilanga and generations to come.
✅ The Minister praised the Wonderful Group of Companies for their strong corporate social responsibility and commitment to national welfare.
✅ ZNS Commander, Lieutenant General Maliti Solochi, said the project supports government policy, placing education at the heart of national transformation.
✅ He added that such initiatives align with ZNS’s tradition of developing education facilities for both military and civilian communities.
✅ Chilanga MP, Honourable Sipho Hlazo, highlighted that Chilanga’s growing population has increased the demand for educational facilities.
✅ The MP said the school’s construction followed his proposal to the Wonderful Group to invest in a community-benefiting secondary school.
✅ He emphasised that education is the greatest gift for children and that Chilanga has made record-breaking progress in education over the past four years through the Constituency Development Fund (CDF).
CDF PROJECTS UPDATE (2024–2025)
✅ St. Michael Secondary – 1×3 classroom block (2025) – works commenced, slab level.
✅ Namalombwe Primary – 1×3 classroom block (2025) – works commenced, setting level.
✅ Mwembeshi Boarding – 400 single mattresses (2025) – delivered.
✅ Mpamba Secondary – 40 double-seater desks (2025) – delivered.
✅ Mt. Makulu Secondary – 340 double-seater desks (2025) – delivered.
✅ Mwembeshi Day Secondary – 160 double-seater desks (2025) – delivered.
✅ Lusaka West Primary – ablution block (2024) – completed.
✅ St. Michael Primary – 40 ECE desks (2025) – delivered.
✅ Bayuni Secondary – 180 desks (2024–2025) – delivered in batches.
✅ Makeni GRZ Secondary – 1×2 science lab with 80 lab stools (2024–2025) – completed and handed over.
✅ Balmora Primary – electrification (2025) – awaiting ZESCO installation.
✅ Shampule Secondary – 320 desks (delivered); 1×3 classroom block (completed); ablution block (completed); borehole and solar pump system (installed).
✅ The groundbreaking was attended by Council Chairperson Mr. Champion Tembo, Councillors, and Council Secretary Mr. Francis Ndola.